Past Projects:
McKesson, San Francisco, CA
197,163 s.f.19 floor re-stack at One Post St. Complete design and
build out of thirteen floors and miscellaneous upgrades to six floors,
to include procurement and management of the following vendors;
asbestos abatement, architect, general contractor, furniture, AV,
IT, Signage, and Move Team. Approximate Project Cost $26M.
McKesson Executive Floor, San Francisco, CA
12,000 s.f. executive floor remodel of a fortune 500 Company's corporate
headquarters. Abating asbestos and completing the construction activities
in the 90 day schedule while the building was occupied made this
job very challenging. The high level of finishes and elaborate audio
visual system makes this one of the finest executive floors in the
area. Project Cost $2.7M; completion December 2002.
Alien Technology Headquarters and Manufacturing Facility,
Morgan Hill, CA
30,000 s.f was designed and built with a wide open office usage.
The remaining 55,000 s.f. was designed for their manufacturing process
of RF Tags, which included H3, H7, and B2 occupancies with multiple
cleanliness levels from class 100 to class 100,000. A complete waste
treatment system for chemical discharge was incorporated. Project
costs were $25 million; completion, February 2002.
Nanometrics, Milpitas, CA
110,000 s.f. corporate headquarters and manufacturing facility.
Included managing the close of escrow for the purchase of the building
and related due diligence reports, entire build out of facility
which contained 20,000 s.f. of class 10,000 clean room, 1,500 s.f.
of class 100 clean room, cafeteria, machine shop, office space,
and work out facility. Project costs $13M; completion November 2001
Science & Engineering Quad, Stanford, CA
150,000 s.f. two building project consisting of research lab and
office space. Both buildings were designed with of steel structure
and limestone skin. The Electrical Engineering building consisted
of primarily of office and classroom space, while the McCullough
Annex has an H7 occupancy and provides labs for chemical research.
Project Costs $75M; completion March 2000.
Applied Materials Tech Center, Santa Clara, CA
167,000 s.f. steel structure, aluminum panel skin, semiconductor
manufacturing facility. Included 40,000 s.f. class 10 ballroom space,
waste treatment area, chiller towers, and office space. Project
Cost $155M; completion December 2000.
Target T119, Newark, CA
130,000 s.f. of interiors and new building. Included approximately
40,000 s.f. of corporate offices and 110,000 s.f. of new store.
This project entailed complete interior demolition of an old Emporium
store, cutting the building in half and adding 40,000 s.f. The second
Vermaport ever installed in the U.S. was part of this project. Construction
cost $18 M; completion in February of 1998.
Blue Arc, San Jose, CA
This project initially consisted of a case study / report to help
Blue Arc break a lease commitment on a building where the shell
was under construction. Keith was able to review the lease and construction
in place and find areas where Blue Arc had merit to terminate their
lease commitment. After successful termination, a new 35,000 s.f.
building was selected and complete T.I. design and construction
was implemented to include a manufacturing lab and office space.
Project Costs $.5M; completion January 2002.
Advent Software, San Francisco, CA
Advent was in the thought process of buying 539 Bryant Street in
San Francisco. A complete observation report was completed to include
a synopsis of the M/E/P systems, structural system, and ADA compliance.
This report weighted Advent's decision on whether or not to buy
the building.
Stiedel Investments San Francisco, CA
Stiedel Investments needed a construction specialist to review their
permitted set of as built drawings and compare them to the existing
building to determine the extent the tenant had completed unauthorized
and un-permitted work. A complete report was delivered to Stiedel
Investments listing all of the areas their tenant had performed
work not in compliant with local codes and jurisdictions. This report
was instrumental in closing a law suite which enabled Stiedel to
recoup the costs associated with putting the building back to compliance.
Solectron, Milpitas, CA
450,000 s.f. new construction of a corporate campus. Included (9)
buildings and common areas. Construction consisted of manufacturing
and all office support groups. Project Costs $21.5M
Xerox Engineering, San Jose, CA
286,000 s.f. of new construction of a corporate campus. Included
(2) concrete tilt up buildings with a connector link. Construction
consisted of R&D, Office Support Groups, and a 15,000 s.f. cafeteria.
Projects Cost $15.5M
Medix Biotech, San Carlos, CA
42,000 s.f. shell upgrade and interior build-out. Included approximately
10,000 s.f. of R&D Labs, 5,000s.f. Vivarium 27,000 s.f. office support
space. Special construction consisted of making significant building
upgrades to turn these two former warehouse buildings into a biotech
laboratory facility." Project Costs$5M
Biocircuits, San Jose, CA
38,000 s.f. interior build out of developer building. Included approximately
10,000 s.f. of R&D labs, 5,000 s.f. of class 1,000 clean room, waste
treat area with sampling pit, 23,000 s.f. of office support area.
Project Costs $5M
|
|