Past Projects:
McKesson Corporation, San Francisco, CA
Space planning and move management for a 19-floor restack project
to include the following:
- Identify specific departments, floor locations
and seat assignments for roughly 1100 people.
- Coordinate and manage construction, furniture,
and IT for swing and interim spaces.
- Move management for all swing and interim space
as well as final seat assignments.
Lucent Technologies, Milpitas, CA
Included relocation / move project management and workplace planning.
Handled move / transition management of all companies purchased
by Lucent. Total scope entailed moving of 1,500 employees within
a 9 building campus.
Rational Software, Cupertino, CA
Included relocation / move project management. Procurement of mover,
janitorial, landscape, and food service vendors as well as complete
move management services. Scope covered 350 people into 100,000
s.f. building.
Netcom, San Jose, CA
Included relocation / move project management. Four phases of move
to include procurement and management of mover, coordination with
and management of end users, and coordination with in house IT group
to ensure correct extension numbers.. Total scope consisted of 450
employees in 130,000 s.f. of offices and labs into two high rise
buildings.
Nanometerics, Milpitas, CA
Included relocation / move project management. Procurement and management
of mover, coordination with and management of end users, and coordination
with in house IT group to ensure correct extension numbers. Total
scope consisted of 190 employees into 110,000 s.f. of manufacturing,
warehouse, and office space.
Bay Networks, Santa Clara, CA
Included relocation / move project management and workplace planning.
Total incorporation of a newly acquired company into existing operations
to include move project management and workplace planning. Additional
work consisted of an ongoing scope of many small project moves.
Business Objects, INC. , San Jose, CA
Included relocation / move project management. Procurement and management
of mover, coordination with and management of end users, and coordination
with in house IT group to ensure extension correct extension numbers.
Total scope consisted of 58,000 s.f. approximately 450 people.
|
|
|